Fall 2023 Project Status – November 2023
All Purpose Room Additions - Kingston, Barton, Sharp, Knight, Johnson and Mann
- The New APR Additions will include a regulation basketball court, a stage, storage, separate entrance to an office area and bathroom to support activities in this new ES specialized space.
- Playground replacements at Johnson, Kingston, Knight, and Mann are also included in this project (equipment to be purchased separately).
- Project is slated to begin in November 2023 after the BOE award to Newport Construction through a competitive bid process on October 17,2023. The new additions are scheduled and contracted to be substantially complete by March of 2025.
- Bid award - $25,191,877
Cherry Hill High School East Stadium Improvements
- Contract awarded to D’Andrea Construction through a competitive bid process on June 27, 2023
- Bid Award - $2,589,000
- Stadium Lighting has been delivered
- Existing field house/storage area to be demolished
- New bleachers expected February of 2024.
- Project is contracted to be substantially complete by March 14, 2023
HVAC Partial Replacement – High School West – D wing
- Using ESSER and SDA Grant Funds to offset cost of equipment and installation
- Work slated to begin over winter break.